Thurston 2019 CB24374 - Substantive Decision
- Complaint number: CB24374
- LBP number: BP106648
- Region: Otago
- Licence class: Carpentry
- Decision date: 11 April 2019
- Penalty: 318(1)f Pay fine 318(4) Pay costs
- Disciplinary grounds: 317(1) b Negligent or incompetent work 317(1) d Work not compliant with building consent 317(1) da Failed to supply certificate / record of work
- Summary: Building consent split into two by main contractor. Respondent carried on with phase two before the consent for it was issued. Respondent negligent for carrying out building work without a building consent. Respondent also failed to deal with changes to the building consents (when issued) as minor variations or amendments. Failure to provide a record of work. Mitigating factors present. Fined $1,500, costs of $1,000.